The commissioning of the complex is the
I quarter of 2025
Status of work:
In the 1st start-up complex works on concreting of a plate of overlapping of the first capture on the 5th floor on a mark +19.0 take place. Concreting of monolithic pylons (6 pcs.), Monolithic walls (2 pcs.), Monolithic beams of the floor slab at the mark -0.03 (2 pcs.) Continues in the 3rd launch complex on the 1st floor at the mark of -4.05. In the 4th start-up complex on the 1st floor at the mark -3.9 concreting of monolithic columns (26 pcs.), Concreting of the wall and staircase (1 pc.) Is carried out. In the 5th start-up complex on the 4th floor at the level of +11.67, concreting of monolithic columns (25 pcs.) And staircase block (1 pc.) Continues.